Full House Renovation
A whole property taken back and rebuilt to a single standard, managed by one team from first drawing to final handover.
Read the guidePractical guidance on planning, costing and living through building work in south west London.
Each service page sets out what the work involves, what drives the cost, how long it takes and what consent you need.

A whole property taken back and rebuilt to a single standard, managed by one team from first drawing to final handover.
Read the guide
Rear, side return and wrap around extensions that open up the ground floor and add genuine value to a London home.
Read the guide
Dormer, mansard, hip to gable and Velux conversions that turn dead roof space into a proper bedroom and ensuite.
Read the guide
Bespoke kitchens installed end to end, including the structural work, services, joinery and stone that sit behind them.
Read the guide
Wetrooms, family bathrooms and ensuites, tanked and tiled properly, with the first fix and second fix handled in house.
Read the guide
Sympathetic refurbishment of period and Victorian stock, from rewires and replastering to full internal reconfiguration.
Read the guideThe single most useful skill when appointing a contractor is knowing what a quote should contain. A figure on one page is not a quote, it is a guess dressed up as one.
What you want is a schedule of works: every item listed in sequence, priced by trade, so you can compare the plastering line on one quote against the plastering line on another. Without that, comparing two contractors is impossible, because you have no idea whether the cheaper one has included the same work.
Look specifically for what is excluded. Common omissions that reappear later as extras are waste removal, scaffolding, making good after first fix, structural calculations, building control fees and the temporary works needed to prop an opening safely.
In our experience the three things that push a project past its date are almost never the construction itself. They are consent, party walls and decisions.
Consent has statutory timescales that cannot be compressed. A planning application takes eight weeks as a target, prior approval notification takes six, and neither starts until the submission is valid. Party wall notices carry response periods, and if a neighbour dissents, surveyors have to be appointed and an award prepared before work can begin.
The third is the one within your control. Decisions on tiles, sanitaryware, kitchen finishes and lighting positions all have lead times attached, and a decision deferred by three weeks frequently costs three weeks on site. We front load those decisions into the schedule so they are made before they become critical.
Many single storey rear extensions and rear dormer loft conversions in south west London do not need a planning application, provided they stay within defined limits on depth, height, volume and materials.
The exceptions matter more than the rule. Flats have no permitted development rights at all. Conservation areas restrict or remove them, and much of Chelsea, Kensington, Brackenbury, Wimbledon Village and parts of Fulham are designated. An Article 4 direction can remove them street by street. Listed buildings need consent for almost anything.
Because designations do not follow neat boundaries, the only reliable answer is to check the specific address. We do that before we quote, so the route we price is the route you can actually take.
A loft conversion is the easiest major project to live through, because the scaffold gives roof access and most of the noise happens above your ceilings. The disruptive phase is the staircase installation, usually a few days.
An extension is manageable until the rear wall comes out, which is a short but significant period, and you will be without a kitchen for part of the programme. A full house renovation is genuinely difficult to live through and is usually both faster and cheaper if the property is empty.
Whatever the project, agree the practicalities before work starts: where the temporary kitchen goes, which route the trades use through the house, what gets sheeted and protected, and what time work starts each morning.
A great deal of the stock in Battersea, Wandsworth and Fulham has already been altered, and not all of it was done properly. Three questions are worth asking before you exchange.
First, did building control sign it off, and is there a completion certificate? Second, do the structural calculations exist for any steels that were installed? Third, was a party wall award made, and does it record the condition of the neighbouring properties?
Missing paperwork is common and often solvable through regularisation or indemnity insurance, but it is far easier to deal with before you buy than during your own sale years later. We are happy to look at what a vendor has provided and tell you where you stand.
We add guidance when there is something genuinely useful to say rather than to a publishing schedule. The service pages carry detailed information on what each type of work involves, what it costs and how long it takes, and the glossary explains the terms that appear on quotes and drawings.
Yes, and we are happy to. Send it over and we will tell you plainly what it covers, what has been left out and whether anything on it looks wrong. You are under no obligation to use us.
Call us and ask. We would rather spend ten minutes on the phone giving you a straight answer than have you make an expensive decision on bad information.